Cloud migration pre-flight checklist
The 20 things you should have decided before your first workload leaves the datacenter. Data model, identity, cost model, exit strategy — the boring stuff that decides whether you land safely.
Most cloud migrations don't fail on the day of cutover. They fail three weeks before, when someone realises a decision that should have been made in month one is still open. This checklist covers the twenty things you should have decided — with the answer written down, agreed with the affected owners — before your first workload leaves the datacenter.
It's intentionally boring. Migrations succeed on discipline, not on new technology.
Business alignment (5)
- The reason. The written reason for the migration is more specific than "we need to be in cloud". Cost reduction, capability, resilience, exit from a lease — one primary driver, agreed with the sponsor.
- The success criteria. Three measurable statements. Not slogans. E.g. "p95 order submission latency ≤ 400 ms", "monthly infra spend ≤ $X after 90 days", "RTO ≤ 30 min for tier-1 workloads".
- The date it can't slip past. Because otherwise the datacenter contract renews / the audit fails / the growth blocks. If no such date exists, the project has no forcing function and will slip.
- The owner. A named executive owner who can approve trade-offs mid-project without a committee. Not "the transformation office".
- The budget. Includes build, migration, first-12-months of run, and a documented 20% contingency. Signed off before RFP.
Architecture & platform (5)
- Cloud provider. Picked and justified — not because a partner recommended it, but because the workload characteristics match. Multi-cloud is usually not the answer for a first migration.
- Landing zone. A written landing-zone design: account/subscription structure, network topology, identity boundary, logging pipeline. Reviewed by security before any workload lands.
- Data model. For every dataset that moves: where the source-of-truth lives during cutover, how consistency is maintained, and what "done" looks like for that dataset.
- Identity boundary. Federation strategy, break-glass account policy, third-party access model. Documented and delegated ownership.
- Observability. Metrics, logs, traces — what's collected, where it lives, who gets paged when. Pre-existing dashboards ported before cutover, not after.
Migration mechanics (5)
- Waves. Workloads grouped into migration waves by dependency, not by organisational chart. Each wave has an entry and exit gate.
- Cutover runbook. Every workload has a written runbook: pre-checks, sequence, decision points, expected duration, rollback trigger, comms points.
- Rollback plan. For every wave, what does "abort" look like operationally? Rehearsed at least once in a non-production wave.
- Data reconciliation. How you prove the destination matches the source. Automated checks that run continuously during the cutover window.
- Business freeze windows. Agreed with the operating teams. Communicated to customers where relevant. Not decided the week before.
Governance & exit (5)
- FinOps model. How costs will be tagged, allocated, reviewed, and controlled after go-live. Alert thresholds set before spend starts.
- Security baseline. Every workload meets the same baseline (encryption in transit + at rest, least-privilege, secret management, audit logging). Documented as code where possible.
- Change process. How production changes get made post-cutover. Who approves. What gets automated.
- Skills plan. Which existing operators become cloud operators. Their training path. Where you'll bring in outside help for the first 6 months.
- Exit strategy. Not a plan to leave — a documented understanding of what it would take to move off this cloud if commercial terms changed materially. Prevents lock-in accidents.
Scoring
- 18–20: You're ready. Start scoping the delivery.
- 14–17: Close the gaps in a 4-week paid discovery, then proceed.
- Below 14: The migration is not the project yet. The decision-making is.