Cloud migration pre-flight checklist

The 20 things you should have decided before your first workload leaves the datacenter. Data model, identity, cost model, exit strategy — the boring stuff that decides whether you land safely.

01
01Loop Team
Editorial

Most cloud migrations don't fail on the day of cutover. They fail three weeks before, when someone realises a decision that should have been made in month one is still open. This checklist covers the twenty things you should have decided — with the answer written down, agreed with the affected owners — before your first workload leaves the datacenter.

It's intentionally boring. Migrations succeed on discipline, not on new technology.

Business alignment (5)

  • The reason. The written reason for the migration is more specific than "we need to be in cloud". Cost reduction, capability, resilience, exit from a lease — one primary driver, agreed with the sponsor.
  • The success criteria. Three measurable statements. Not slogans. E.g. "p95 order submission latency ≤ 400 ms", "monthly infra spend ≤ $X after 90 days", "RTO ≤ 30 min for tier-1 workloads".
  • The date it can't slip past. Because otherwise the datacenter contract renews / the audit fails / the growth blocks. If no such date exists, the project has no forcing function and will slip.
  • The owner. A named executive owner who can approve trade-offs mid-project without a committee. Not "the transformation office".
  • The budget. Includes build, migration, first-12-months of run, and a documented 20% contingency. Signed off before RFP.

Architecture & platform (5)

  • Cloud provider. Picked and justified — not because a partner recommended it, but because the workload characteristics match. Multi-cloud is usually not the answer for a first migration.
  • Landing zone. A written landing-zone design: account/subscription structure, network topology, identity boundary, logging pipeline. Reviewed by security before any workload lands.
  • Data model. For every dataset that moves: where the source-of-truth lives during cutover, how consistency is maintained, and what "done" looks like for that dataset.
  • Identity boundary. Federation strategy, break-glass account policy, third-party access model. Documented and delegated ownership.
  • Observability. Metrics, logs, traces — what's collected, where it lives, who gets paged when. Pre-existing dashboards ported before cutover, not after.

Migration mechanics (5)

  • Waves. Workloads grouped into migration waves by dependency, not by organisational chart. Each wave has an entry and exit gate.
  • Cutover runbook. Every workload has a written runbook: pre-checks, sequence, decision points, expected duration, rollback trigger, comms points.
  • Rollback plan. For every wave, what does "abort" look like operationally? Rehearsed at least once in a non-production wave.
  • Data reconciliation. How you prove the destination matches the source. Automated checks that run continuously during the cutover window.
  • Business freeze windows. Agreed with the operating teams. Communicated to customers where relevant. Not decided the week before.

Governance & exit (5)

  • FinOps model. How costs will be tagged, allocated, reviewed, and controlled after go-live. Alert thresholds set before spend starts.
  • Security baseline. Every workload meets the same baseline (encryption in transit + at rest, least-privilege, secret management, audit logging). Documented as code where possible.
  • Change process. How production changes get made post-cutover. Who approves. What gets automated.
  • Skills plan. Which existing operators become cloud operators. Their training path. Where you'll bring in outside help for the first 6 months.
  • Exit strategy. Not a plan to leave — a documented understanding of what it would take to move off this cloud if commercial terms changed materially. Prevents lock-in accidents.

Scoring

  • 18–20: You're ready. Start scoping the delivery.
  • 14–17: Close the gaps in a 4-week paid discovery, then proceed.
  • Below 14: The migration is not the project yet. The decision-making is.

If you'd like a second pair of eyes on where you land on this checklist, book a 30-minute consultation. We'll walk through it with you and tell you honestly whether we're the right team to help.